Circle Park Improvements Coming Your Way!
Published 9/27/2021
A new and improved Circle Park path and parking lot are coming your way!
Work begins September 29 on new concrete ADA parking stalls near the south end of Circle Park, as well as the accessible ramp that connects to the Westfield Middle School parking lot on the north end of the park.
Parking lot asphalt patching and restriping, along with path resurfacing, is scheduled to begin October 11. The path will be usable at the end of each day, as the gravel will be compacted and rolled smooth. If a section of path needs to be closed overnight (which is not anticipated), it will be marked with a “Path Closed” sign.
View the aerial image of the work to be completed.
Thank you for your patience while we make these important accessibility improvements.